On Friday afternoon the 21st, just prior to Thanksgiving, it looked as if it might be too windy to install the cab, well the weather reports were wrong and Saturday morning turned out beautiful. After some measuring and re-thinking of how to get the cab on, we opted to pull our roll up door up as tight as possible and pull the locomotive out of the tent, install the cab and push the engine back in. After easily rolling the engine out, some rigging, and doing a little tree trimming we were ready to set the cab on. With Doug Mull at the wheel of the forklift the cab came went on with almost no fight, we only had to trim one very small piece of the new angle iron cab frame.
With the cab on, we gently moved the engine back inside and cleared the tent door by only about 1/4″! Once safely back inside two new brackets were constructed and the rest of the cab bolts installed. With the exception of a few bolts, the cab is back on and secured and it sure does look good!
With the cab on we went about completing the brake rigging. Jeff and Bob spent the afternoon in and under the engine finishing up pinning and adjusting the brake rigging while Ashley got the plumbing cleaned up to air up the brake cylinder which had already been rebuilt. By Sunday we had aired up and adjusted the brakes and things looked good. With a little more minor adjusting the brakes will be done.
Up on top of the boiler we also got the new lubricator lines roughed into place. While there is still a bit more work to go they are on their way towards completion. Also on top the stainless steel wire was wrapped around the boiler shell in order to hold the insulation in
place. We also finished the large 3-1/4″ boiler plug on the wrapper sheet that was in need of tapping and machining. Having a lathe just up the street we can use whenever needed sure is a huge help.
Lastly, we were ready to reinstall the dry pipe tee in the smoke box until we realized that all our moving around of things had made the dry pipe – flue sheet joint start to leak. After some head scratching and sleeping on it Saturday night it was decided to remove the throttle – which we had to do anyways for the interior inspection – and to see if we could easily remove the dry pipe and clean the seats. Well we could, and did, easily remove the dry pipe. After cleaning and reseating it, the pipe was reinstalled with the tee much quicker and easier than any of us expected and is awaiting a hydro test. All in all it was a very productive weekend.
Although we will possibly work in December, with the holidays and personal commitments, this may have been our last work weekend for 2014. If it is we can look back an be thrilled with all of our accomplishments this year. And don’t forget to do some Christmas shopping in our store or make a tax deductible donation before the end of the year.
And as always…we couldn’t do it without your support!
You must be logged in to post a comment.